Amtrak Timeliness Study Results

September, 2004

Michigan Association of Railroad Passengers (MARP) has conducted a timeliness study for AMTRAK trains serving the state of Michigan. The study period covers September 1 through September 30, 2004. Data for the study was obtained directly from AMTRAK’s website-based train status database.

Data was collected by four MARP members who were each assigned specific trains: Blue Water-Kaz Fujita; Pere Marquette-John Langdon; Wolverine eastbound-Jim Wallington; and Wolverine westbound-Mike Whims. MARP wishes to thank these members for their valuable efforts.

The study was prompted by continued complaints from passengers regarding AMTRAK’s timeliness performance. A preliminary study conducted by MARP in June-July, 2004 indicated serious timeliness delays, some of which were considered perhaps due to startup problems on the Blue Water and other non-recurring events. The September study is both a confirmatory study and a baseline against which future studies will be compared.

The results of the September study indicate that serious deficiencies exist in AMTRAK’s ability to deliver timely service on Michigan’s ten (10) daily trains. On average, an eastbound passenger could rely on reaching a train’s final Michigan destination city on-schedule only 36% of the time, and a westbound passenger could rely on an on-schedule arrival in Chicago only 9% of the time.

The September study results indicate that performance varies from train to train. The westbound trips are clearly less reliable than eastbound, and the somewhat subjective honor of the worst performance is shared by the Blue Water westbound and the Wolverine mid-day westbound #353 trains. In fact, anyone who rode the #353 Wolverine train never reached Chicago on time during September.

This report includes a summary sheet of performance data by train, followed by the actual data collected by each member. Although data format used by each member differs, a standard convention is utilized where (+) indicates lateness. Also, an early arrival is counted as on time in the summaries. A cancelled train (due to freight problems for instance) was not counted in the averaging.

      MICHIGAN ASSOCIATION OF RAILROAD PASSENGERS				
                 September, 2004 AMTRAK Timeliness Study Results				

BLUE WATER West #365 			Dp PTH	Dp LNS	Dp BTL	Ar CHI
% of time train met schedule		90%	20%	7%	3%
Ave. departure from schedule (min.)	0.8	32.8	45.0	71.8

BLUE WATER East #364 			Dp CHI	Dp BTL	Dp LNS	Ar PTH
% of time train met schedule		87%	10%	0%	30%
Ave. departure from schedule (min.)	7.5	27.4	37.6	39.4

PERE MARQUETTE West #371 		Dp GRR	Dp HOM	Dp NBM	Ar CHI
% of time train met schedule		100%	7%	3%	10%
Ave. departure from schedule (min.)	0.0	6.3	18.6	25.5

PERE MARQUETTE East #370 		Dp CHI	Dp NBM	Dp HOM	Ar GRR
% of time train met schedule		90%	28%	24%	31%
Ave. departure from schedule (min.)	0.4	14.3	16.3	14.3

WOLVERINE early West #351 		Dp PNT	Dp DET	Dp BTL	Ar CHI
% of time train met schedule		69%	0%	0%	10%
Ave. departure from schedule (min.)	5.1	18.9	33.1	32

WOLVERINE mid-day West #353 		Dp PNT	Dp DET	Dp BTL	Ar CHI
% of time train met schedule		38%	0%	0%	0%
Ave. departure from schedule (min.)	14.7	26.6	46.0	42.5

WOLVERINE evening West #355 		Dp PNT	Dp DET	Dp BTL	Ar CHI
% of time train met schedule		79%	18%	3%	23%
Ave. departure from schedule (min.)	7.5	19.6	30.4	28.3

WOLVERINE early East #350 		Dp CHI	Dp BTL	Dp DET	Ar PNT
% of time train met schedule		80%	17%	30%	30%
Ave. departure from schedule (min.)	9.8	25.3	29.5	31.9

WOLVERINE mid-day East #352 		Dp CHI	Dp BTL	Dp DET	Ar PNT
% of time train met schedule		83%	23%	17%	20%
Ave. departure from schedule (min.)	3.8	25.3	30.6	29.1

WOLVERINE evening East #354 		Dp CHI	Dp BTL	Dp DET	Ar PNT
% of time train met schedule		90%	20%	33%	30%
Ave. departure from schedule (min.)	1.1	15.6	15.1	16.3

Data source: AMTRAK

Detroit Commuter Rail Proposal

SOME COMMUTER RAIL SERVICE FACTS RELEVANT TO DETROIT

 

 


Prepared for the Michigan Association of Railroad Passengers, Inc. and
Transportation Riders United, Inc.
by Dietrich R. Bergmann, PhD, PE
Railway Systems Engineering Corporation

 

 

Text for this page prepared on 28 May 2001 and last updated on 29 May 2001

 

 

 

 

Commuter rail service makes use of existing railroad rights of way and tracks, which on some occasions must be upgraded to accommodate the commuter rail service. It is distinct from other rail-based public transportation services known often as “trolley”, “streetcar”, “light rail”, or “heavy-rail” services.

Commuter rail service exists in a number of North American metropolitan areas. The accompanying web page enumerates many of these and includes links to their web sites so you can see how commuter rail services are being developed elsewhere in the United States and Canada. The population of some of these metropolitan areas is smaller than Metro Detroit’s population.

Commuter rail service between Detroit’s Renaissance Center and Pontiac can be readily established, notwithstanding the fact that the downtown segment of the right of way used for such a service until 1983 must be rehabilitated and new passenger coaches and locomotives must be purchased. The right-of-way rehabilitation is a matter of several months work to begin a rudimentary form of the service. Determining and implementing a means to extend the service in downtown Detroit through, under, or around the General Motors Corporation’s ten-story parking structure constructed during year 2000 just west of Rivard, behind Christ Chruch between Franklin and Atwater Streets, will take additional time. See MARP’s and TRU’s joint 24 May 2001 press release for information about the speed with which new passenger coaches and locomotives can be obtained for a demonstration project.

MDOT sponsored a study completed in 1997 that estimated the investment, the travel time performance, patronage, and operating cost subsidy for inauguration of commuter rail services on seven metro Detroit routes. MDOT’s study assumed that used passenger coaches and used locomotives would be purchased for the commuter rail service. RSE recommends against the purchase of used passenger coaches and used locomotives because use of new low-floor bi-level coaches enables the development of shorter trip times for the passengers and facilitates railcar access and egress by both handicapped and non-handicapped passengers.

RSE’s November 2000 calculation of the start up cost for a Detroit Renaissance Center – Oakland County commuter rail service estimates an investment of $85,000,000. The estimate is based on the investment estimated in MDOT’s study concluded during 1997. Details are given on the attached investment summary.

Station stops and service run times for the Renaissance Center – Pontiac service abandoned in 1983, for the replacement service considered by MDOT in 1997, and for the service that uses modern equipment and that is feasible at this time are provided on the attached service summary.

Have you considered what the benefits are from using quality public transportation for travel in lieu of a private automobile? One of those benefits is the reduction in the costs of traffic accidents. The Michigan Department of State Police has estimated that the Michigan economy suffered a loss of $9.6 billion during calendar year 1999 due to traffic crashes. Turn to the attachment , soon to be available, to see how significant the accident cost savings can be when people use a train to travel to their jobs in downtown Detroit, the Detroit Medical Center, the Wayne State University/Detroit Cultural Center campuses, Detroit’s New Center area, Royal Oak, Troy, Pontiac, or other places in the corridor extending from Detroit’s Renaissance Center to and beyond Pontiac.

The Southeast Michigan Council of Governments (SEMCOG) during mid-2000 initiated a “Transit Visioning” process for metro Detroit. Comments have been solicited on several occasions and SEMCOG staff recommendations will be considered by SEMCOG’s General Assembly at that body’s October 2001 meeting. A flyer containing a vision regarding commuter rail service for the corridor extending from Detroit’s Renaissance Center to Oakland County was distributed on behalf of TRU and MARP to members of the public just before the beginning of SEMCOG’s 09 May 2001 “Transit Visioning” session held at the Troy Marriott Hotel. The commentary attached hereto is based on that statement invites you to support that vision by taking several actions.

RECENT ACTIONS BY GOVERNMENTAL BODIES IN SUPPORT OF ESTABLISHING MODERN COMMUTER RAIL SERVICE IN THE CORRIDOR BETWEEN DETROIT’S RENAISSANCE CENTER AND OAKLAND COUNTY

The City of Ferndale’s Council on 19 December 2000 passed a resolution supporting the establishment of commuter rail service in lieu of widening highways. See the attachment for the full test of that resolution.

The Birmingham’s City Commission on 22 January 2001 passed a resolution that is similar to Ferndale’s resolution. Kenneth Rogers, Oakland County’s Deputy County Executive, on 16 March 2001 sent a letter to Birmingham’s Mayor and City Commission that was critical of their 22 January 2001 resolution, attaching at the end of it a marked up copy of the resolution. Bergmann was given Mr. Rogers’ letter for comment and responded in a 06 April 2001 letter to the City of Birmingham. The Birmingham City Commission voted unanimously on 23 April 2001 to send Bergmann’s letter to Mr. Rogers without comment. See the attachment for the Bergmann letter followed by the relevant excerpt from the Birmingham City Commission’s minutes and its Clerk’s letter to Mr. Rogers.

The Detroit City Planning Commission passed a resolution on 19 January 2001 asking that a full Environmental Impact Statement (EIS) be undertaken by MDOT on MDOT’s proposed I-375 extension project (estimated cost: $72 million) and MDOT’s proposed Oakland County I-75 widening project (estimated cost: $447 million) and that a Detroit Renaissance Center – Oakland County commuter rail service be considered as an alternative to parts or all or all of those two projects. After considerable pressure from MDOT, GM, and the Detroit Mayor’s office, the Detroit City Planning Commission substituted for the 19 January 2001 resolution a resolution that asks for a revision of the MDOT’s October 2000 I-375 Environmental Assessment (EA) that takes into account commuter rail for the Detroit Renaissance Center – Oakland County corridor.

Although the City of Troy has not passed a resolution, it has purchased land along the Detroit-Oakland County commuter rail route for a future Transportation Center. However, a provision of the Consent Court Decree that conveyed that property to the City of Troy provides that it shall return to the prior owner if not developed by the City of Troy for public transportation services within ten years [of 02 June 2000]